Re: Planning the Fineract 1.3 Release


+1

> 
>     On December 11, 2018 at 8:09 PM Ed Cable <edcable@xxxxxxxxx> wrote:
> 
>     Hi all,
> 
>     This to continue the discussion on the planning of the 1.3 release. With
>     the slight delays in 1.2, we're a little more than a week behind schedule
>     for 1.3. The wiki page (
>     https://cwiki.apache.org/confluence/display/FINERACT/1.3.0+-+Apache+Fineract)
>     has been updated with the new schedule to reflect the following:
> 
>     QA: Dec 14 - 26
>     Publish Release Notes: Dec 26
>     Vote on Release: Jan 1
>     Target Release Date: Jan 7
> 
>     The list of tickets that are ready to be merged or currently under
>     development has been updated at 1.3.0. No additional tickets will be added
>     to the scope of the 1.3.0 release - any new contributions that get raised
>     will be targeted for the 1.4.0 release.
> 
>     Some of the enhancements to be included include the GSIM and GLIM work led
>     by Nikil, performance enhancements including parallelization of batch jobs
>     led by Kumaranath, and the notifications framework done previously by
>     Courage.
> 
>     *Help the community out and build merit!*
>     P1 bugs that couldn't be addressed during this release cycle have been
>     tagged with 1.4.0 fix version. We welcome any volunteer contributors to
>     work on some of these P1 issues.
> 
>     Once again, I ask that if you have a contribution that you've worked on or
>     would like to make, please begin discussing it on-list so we can aim to get
>     it into 1.4.0.
> 
>     The planned cutoff date for new features going into 1.4.0 is January 7. See
>     more details at
>     https://cwiki.apache.org/confluence/display/FINERACT/1.4.0+-+Apache+Fineract
> 
>     On Wed, Nov 21, 2018 at 9:56 AM Ed Cable <edcable@xxxxxxxxx> wrote:
> 
>         > > 
> >         Hello Community,
> > 
> >         Earlier in the year we discussed and adopted a schedule for targeting
> >         monthly releases. We're going to try and achieve that with the forthcoming
> >         1.3 release.
> > 
> >         This email hearby kicks off the planning process for the Fineract 1.3
> >         release. I've included the table discussing what is occurring at each phase
> >         and how it differed from our previous processes.
> > 
> >         So between now and November 30, on this email thread and in JIRA and the
> >         release planning page, I want any individuals in the community whether
> >         you're a volunteer, an intern, or a partner that's built out functionality,
> >         to discuss and share if you have code that you would like to and think it'd
> >         be ready to contribute for the 1.3 release.
> > 
> >         The code should be near complete at this stage so if you do have a
> >         contribute you want to make but it's still in progress, that can be
> >         targeted for a future release, i.e. 1.4
> > 
> >         Please discuss on this thread, add to this wiki page or open and tag
> >         tickets with the release fix version of 1.3.0
> > 
> >         Release Page on Wiki:
> >         https://cwiki.apache.org/confluence/display/FINERACT/1.3.0+-+Apache+Fineract
> >         JIRA Filter for Issues Tagged 1.3.0:
> >         https://issues.apache.org/jira/issues/?filter=12345265
> > 
> >         Plans for Release Apache Fineract 1.3
> > 
> >         Planning Release - Start Discussion on November 21
> > 
> >         Announce Release - Nov 30
> > 
> >         QA - Nov 30 - Dec 14
> > 
> >         Publish Release Notes - December 14
> > 
> >         Vote on Release - December 21
> > 
> >         Target release date - December 28
> > 
> >         Stage
> > 
> >         Description
> > 
> >         Proposed Length
> > 
> >         How Far in Advance of Release (Proposed)
> > 
> >         How Far in Advance of Release (Currently)
> > 
> >         Planning of Next Release
> > 
> >         Discuss with community what would like to ship in next release and what
> >         people could work on.
> > 
> >         Create fix version on JIRA to assign to.
> > 
> >         Action: modify existing email template to open up planning process,
> >         schedule a meeting to discuss and set a tentative branching date (i.e. 2
> >         weeks later, if release date is a month past that).
> > 
> >         .
> > 
> >         1 week
> > 
> >         6 weeks
> > 
> >         Doesn’t Exist
> > 
> >         Announcement of Release
> > 
> >         Announce what is going to come in the release (should be 80% done at
> >         least).
> > 
> >         Cut a release branch and freeze release branch and then develop branch
> >         can still have active work on it but only in rare cases might anything
> >         additional from develop
> > 
> >         Email out sharing release branch details
> > 
> >         4 weeks prior
> > 
> >         1 - 2 months
> > 
> >         QA
> > 
> >         QA begins on the release branch - staging Server setup
> > 
> >         Might fix some regression issues
> > 
> >         1 - 2 weeks
> > 
> >         4 weeks prior
> > 
> >         JIRA Sanitization/Publish RElease Notes
> > 
> >         Sanitize release documentation
> > 
> >         Create release notes and email community release information with links.
> > 
> >         2 weeks prior
> > 
> >         Vote
> > 
> >         Create artifacts, sign release, etc. Open up votes
> > 
> >         1 week prior
> > 
> >         Release
> > 
> >         Tally up votes, announce, update websites and infrastructure with new
> >         release artifacts.
> > 
> >     > 
>     --
>     *Ed Cable*
>     President/CEO, Mifos Initiative
>     edcable@xxxxxxxxx | Skype: edcable | Mobile: +1.484.477.8649
> 
>     *Collectively Creating a World of 3 Billion Maries | *http://mifos.org
>     <http://facebook.com/mifos> <http://www.twitter.com/mifos>
>